October 2023--The Town is nearing completion of the construction documents and will be going out to bid for a general contractor in February 2024. We expect to start construction in the summer of 2024. The final design features an 11,000+ square foot building with a full-sized cross-court gymnasium, multipurpose/programming room, storage rooms, lobby/reception, staff offices, and restrooms. Site development includes paving of the alley, curbs, sidewalks, outdoor space, and parking lot. The site plans also include a splash pad (north of the Community Center), which will likely be phased to 2025.

Property Acquisition, Outreach, Design & Construction Costs

Total project estimated cost: $9,300,000

Funding source: American Rescue Plan Act Funds $1,000,000 + Grant for $1,500,000 + Impact Funds $6,800,000 

Schedule

2021: The Town of Mead officially closed on the old bean plant property at 401 3rd Street in downtown Mead.

2021-2022: Community outreach, resident feedback, priority programming, preliminary design scope, and estimated budget costs.

2022-2023: Demolition of site & grading, reuse of bean plant materials, final design, detail budget, construction documents

2023-2024:  Community Development Review

2024: Project Bidding

2024-2025: Construction